Activity
- 24 NovCucurel requested your approval on label artwork v3.
- 20 NovVendor reported mid-run QC passed. Evidence not yet attached, so the milestone stays "reported".
- 10 NovVendor confirmed production start with batch record BR-7781.
- 5 NovVendor confirmed schedule: complete 12 Dec.
- 3 NovYou paid deposit INV-0931, $10,000.
- 1 NovYou issued PO-1042.
Documents
- Agreement_Northwind_v1.pdf8 Oct
- Spec_sheet_locked.pdf31 Oct
- PO-1042.pdf1 Nov
- INV-0931_deposit.pdf3 Nov
- Label_artwork_v3.pdf24 Nov